EstatePass
Contract AdminPermitsmedium20% of exam part

What is the maximum monetary limit for work performed under a Registered General Contractor license in Florida?

Correct Answer

D) $300,000 per project

A Registered General Contractor license in Florida has a monetary limit of $300,000 per project. Projects exceeding this amount require a Certified General Contractor license.

Answer Options
A
No monetary limit
B
$200,000 per project
C
$500,000 per project
D
$300,000 per project

Why This Is the Correct Answer

Under Florida law, a Registered General Contractor license allows contractors to perform work up to $300,000 per project. This monetary limitation is specifically established in Florida Statutes Chapter 489 to differentiate between registered and certified contractor classifications. Any construction project exceeding $300,000 requires the contractor to hold a Certified General Contractor license, which has no monetary limitations. This threshold ensures that larger, more complex projects are handled by contractors with higher qualifications and bonding requirements.

Why the Other Options Are Wrong

Option A: No monetary limit

$200,000 is below the actual limit established by Florida law for Registered General Contractors and would be too restrictive for this license classification.

Option C: $500,000 per project

$500,000 exceeds the monetary limit for Registered General Contractors and would encroach into the territory requiring a Certified General Contractor license.

Memory Technique

Think 'Registered = Restricted to $300K' - both words start with 'R' and the number 3 represents the restriction at $300,000.

Reference Hint

Florida Statutes Chapter 489 - Construction Industry Licensing, specifically Section 489.105 regarding contractor classifications and monetary limitations

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.