What is the maximum monetary limit for work performed under a Registered General Contractor license in Florida?
Correct Answer
D) $300,000 per project
A Registered General Contractor license in Florida has a monetary limit of $300,000 per project. Projects exceeding this amount require a Certified General Contractor license.
Why This Is the Correct Answer
Under Florida law, a Registered General Contractor license allows contractors to perform work up to $300,000 per project. This monetary limitation is specifically established in Florida Statutes Chapter 489 to differentiate between registered and certified contractor classifications. Any construction project exceeding $300,000 requires the contractor to hold a Certified General Contractor license, which has no monetary limitations. This threshold ensures that larger, more complex projects are handled by contractors with higher qualifications and bonding requirements.
Why the Other Options Are Wrong
Option A: No monetary limit
$200,000 is below the actual limit established by Florida law for Registered General Contractors and would be too restrictive for this license classification.
Option C: $500,000 per project
$500,000 exceeds the monetary limit for Registered General Contractors and would encroach into the territory requiring a Certified General Contractor license.
Memory Technique
Think 'Registered = Restricted to $300K' - both words start with 'R' and the number 3 represents the restriction at $300,000.
Reference Hint
Florida Statutes Chapter 489 - Construction Industry Licensing, specifically Section 489.105 regarding contractor classifications and monetary limitations
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Your project requires a crane for 15 days. The crane can be rented for $800 per day or purchased for $45,000 with a resale value of $38,000. Operating costs are $200 per day regardless of ownership. Which option is more cost-effective?
Next Question
A residential subdivision requires 15 building permits. The jurisdiction charges a plan review fee of $125 per permit plus a $50 administrative fee per application. If all permits are submitted together as one application, what is the total plan review cost?
