A material supplier delivers lumber worth $12,000 on April 10th. The project is completed on May 20th. Under ORS 87, what is the supplier's lien filing deadline?

Correct Answer

D) August 3rd

Material suppliers have 75 days from project completion to file liens under ORS 87. From May 20th completion date, 75 days later is August 3rd.

Answer Options
A
June 24th
B
July 24th
C
July 4th
D
August 3rd

Why This Is the Correct Answer

August 3rd is correct. Under ORS 87, material suppliers have 75 days from project completion to record a lien claim. The project completed on May 20th. Counting 75 days from May 20th: May has 11 remaining days (May 21–31), June has 30 days (11+30=41 days), July has 31 days (41+31=72 days), then 3 more days into August = August 3rd. The lien must be recorded by August 3rd.

Why the Other Options Are Wrong

Option A: June 24th

June 24th is incorrect. June 24th would be only 35 days after May 20th — less than half the 75-day deadline. This may be confused with the 30-day or 35-day deadlines that apply in other lien contexts.

Option B: July 24th

July 24th is incorrect. July 24th is 65 days after May 20th, which is 10 days short of the correct 75-day period. This is a close distractor testing whether you know the precise deadline.

Option C: July 4th

July 4th is incorrect. July 4th is only 45 days after May 20th. This may be a distractor based on confusing the 45-day notice of right to lien period with the 75-day lien filing deadline.

Memory Technique

ORS 87 lien deadlines: Prime contractors have 75 days from project completion; material suppliers also have 75 days from completion (not from delivery). Remember: the clock starts at completion, not delivery. '75 days to lien — count from done, not from delivery.'

Was this explanation helpful?

More Oregon Questions

Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?

An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?

A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?

Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?

A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?

A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.

A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?

What is the minimum experience requirement for obtaining an Oregon CCB contractor license?

A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?

A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.