EstatePass
CaliforniaContractsmedium20% of exam part

A material supplier delivers $3,500 worth of lumber to a job site on January 10th. The supplier is not paid and wants to file a mechanics lien. What is the deadline for recording the lien?

Correct Answer

B) April 10th

Material suppliers have 90 days from the date they last furnished materials to record a mechanics lien. January 10th + 90 days = April 10th.

Answer Options
A
July 10th
B
April 10th
C
February 9th
D
March 11th

Why This Is the Correct Answer

Under California Civil Code §8412, a claimant who is not the direct contractor must record a mechanics lien within 90 days after the date they last furnished labor or materials. January 10 + 90 days = April 10th. The supplier's last furnishing date is January 10th, so the deadline is April 10th.

Why the Other Options Are Wrong

Option A: July 10th

Incorrect. July 10th would be 180 days from January 10th, which is double the actual 90-day window. No California provision gives material suppliers 180 days to record a lien.

Option C: February 9th

Incorrect. February 9th is only 30 days from January 10th. This is too short — 30 days relates to other construction notice deadlines (e.g., some preliminary notice periods), not the mechanics lien recording deadline for suppliers.

Option D: March 11th

Incorrect. March 11th is approximately 60 days from January 10th. While 60 days is the deadline for direct contractors (prime contractors) to record a lien after project completion, material suppliers and subcontractors have 90 days from their last work/delivery date.

Memory Technique

Suppliers get '90 days' — think '9-0' like a right angle (90°), which is a square corner, like a solid supplier standing their ground. Prime contractors get 60 days from completion. 90 > 60, suppliers get more time.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.