A material supplier delivers $12,000 in lumber to an Oregon residential project on March 15th. The last delivery was April 8th. What is the deadline to record a lien under ORS 87?

Correct Answer

A) June 22nd

Material suppliers have 75 days from the last delivery to record a lien. From April 8th, 75 days later is June 22nd.

Answer Options
A
June 22nd
B
July 8th
C
May 8th
D
June 12th

Why This Is the Correct Answer

Under ORS 87, material suppliers have 75 days from the date of last delivery to record a lien. The last delivery was April 8th. Counting 75 days forward from April 8th: April has 22 remaining days (April 9–30), May has 31 days (22+31=53), June has 30 days but we only need 22 more (53+22=75), landing on June 22nd.

Why the Other Options Are Wrong

Option B: July 8th

July 8th would be 91 days (approximately 3 months) after April 8th — this exceeds the 75-day statutory window and would result in loss of lien rights.

Option C: May 8th

May 8th is only 30 days after April 8th. While 30 days is a common deadline in other contexts (e.g., notice of right to lien), it is not the lien recording deadline for material suppliers under ORS 87.

Option D: June 12th

June 12th is 65 days after April 8th. This is close to but short of the actual 75-day window, and does not correspond to any statutory deadline under ORS 87.

Memory Technique

Think '75 from last' — the lien clock starts on the LAST delivery day, not the first. If you remember '75 days from last delivery,' you can always count forward accurately on the exam.

Was this explanation helpful?

More Oregon Questions

Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?

An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?

A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?

Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?

A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?

A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.

A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?

What is the minimum experience requirement for obtaining an Oregon CCB contractor license?

A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?

A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.