A homeowner wants to finish a basement and install a bathroom. The basement floor is 7 feet below the main sewer line. What type of system is required according to Michigan plumbing standards?

Correct Answer

B) Sewage ejector pump system

When fixtures are below the main sewer line, Michigan plumbing code requires a sewage ejector pump system for proper drainage.

Answer Options
A
Grinder pump system
B
Sewage ejector pump system
C
Gravity drainage system
D
Septic system connection

Why This Is the Correct Answer

A sewage ejector pump system is required when plumbing fixtures are located below the elevation of the main sewer line. The pump collects waste in a sealed basin and forces it upward under pressure to reach the gravity sewer. Michigan plumbing code mandates this system to prevent backflow and ensure proper sanitary drainage.

Why the Other Options Are Wrong

Option A: Grinder pump system

A grinder pump system is a specific type of pressure sewer system used to pump sewage from a property to a municipal main, typically for entire homes in low-lying areas. It grinds solids and pumps effluent long distances, but it is not the standard code-required solution for a single below-grade bathroom fixture group in Michigan residential construction.

Option C: Gravity drainage system

A gravity drainage system relies solely on slope (typically 1/4 inch per foot) to move waste to the sewer. When fixtures are 7 feet below the main sewer line, gravity flow is physically impossible β€” waste cannot travel uphill without mechanical assistance.

Option D: Septic system connection

A septic system connection is used for properties not served by public sewer, and handles all household waste. It is not a solution for routing below-grade fixtures to an existing sewer connection, and installing a new septic system in this context would be unnecessary, impractical, and code-noncompliant.

Memory Technique

Think 'EJECT what's below.' When fixtures are below the sewer, you need to EJECT the waste upward β€” Sewage Ejector Pump. Picture an elevator pushing waste up from a basement pit to reach the sewer level.

Was this explanation helpful?

More Michigan Questions

A residential foundation wall in Michigan is 8 feet high with 2 feet above grade. The backfill exerts lateral pressure of 30 psf per foot of depth. What is the maximum lateral pressure at the bottom of the foundation wall?

A builder discovers that the electrical service entrance was installed without proper permits. According to Michigan law, what is the most appropriate next step?

What is the maximum allowable span for a 2x8 floor joist (Grade 2 Douglas Fir) at 16" O.C. with 40 psf live load and 10 psf dead load according to Michigan Building Code span tables?

According to Michigan Building Code, what is the maximum height of a wood-framed bearing wall using 2x4 studs with standard construction?

A homeowner requests to convert a bedroom into a bathroom on the second floor. What is the primary Michigan code concern the builder must address?

According to Michigan plumbing regulations, what is the minimum pipe size required for a water service line serving a single-family residence?

A contractor is building a basement foundation wall that is 8 feet high and will retain 6 feet of soil. What is the minimum wall thickness required by the Michigan Building Code for poured concrete?

A homeowner wants to install a gas fireplace in their living room. The contractor notices the existing gas line is 1/2 inch black iron pipe. For a 40,000 BTU fireplace with a 25-foot run, is this pipe size adequate according to Michigan gas code?

During a framing inspection, the building official notes that the contractor used 2x4 studs at 24 inches on center for an exterior wall. According to Michigan Building Code, what is the maximum wall height allowed for this configuration?

A contractor is installing a beam to support floor joists. The beam must carry a total load of 8,000 pounds over a 12-foot span. If the allowable fiber stress for the lumber grade is 1,200 psi, what is the minimum required section modulus?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.