A homeowner wants to cancel a $12,000 roofing contract signed at their home on Friday. They attempt to cancel on the following Tuesday by email. Is this cancellation valid?

Correct Answer

A) Yes, if the email is sent before midnight Tuesday

The homeowner has until midnight of the third business day (Tuesday) to cancel, and written notice includes email under California law.

Answer Options
A
Yes, if the email is sent before midnight Tuesday
B
No, because email is not an acceptable form of cancellation
C
No, because the 3-day period has expired
D
Yes, but only if the contractor accepts the email cancellation

Why This Is the Correct Answer

California's Home Solicitation Sales Act (Civil Code 1689.5 et seq.) gives homeowners three business days to cancel a contract signed at their home. Friday is day zero; Saturday = day 1, Monday = day 2, Tuesday = day 3. The homeowner has until midnight Tuesday to cancel. California also recognizes email as written notice of cancellation, so the email sent before midnight Tuesday is valid.

Why the Other Options Are Wrong

Option B: No, because email is not an acceptable form of cancellation

Email is acceptable written notice under California law for contract cancellation. There is no requirement that cancellation be by certified mail or hand delivery, though those methods are also valid.

Option C: No, because the 3-day period has expired

The 3-day period has NOT expired by Tuesday. Business days are counted: Saturday is day 1, Sunday is typically excluded (non-business day), Monday is day 2, and Tuesday is day 3. The deadline is midnight Tuesday, so a Tuesday cancellation is within the window.

Option D: Yes, but only if the contractor accepts the email cancellation

The contractor's acceptance is irrelevant. The right to cancel under the Home Solicitation Sales Act is a statutory right; the contractor cannot waive it or condition it on their acceptance. The homeowner's timely notice is sufficient.

Memory Technique

Remember: 'Friday + 3 = Tuesday midnight.' Count on your fingers: Friday (sign) → Saturday (1) → Monday (2) → Tuesday (3). Email = valid written notice. The contractor's opinion does not matter.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.