A homeowner requests a change order to add a 200 square foot room addition. The original contract was for $180,000. Michigan law requires change orders to be:

Correct Answer

B) Written and signed by both parties

Michigan construction law requires all change orders to be in writing and signed by both parties, regardless of amount, to be legally enforceable.

Answer Options
A
Notarized if over 10% of original contract value
B
Written and signed by both parties
C
Verbal agreements are sufficient if under $5,000
D
Approved by the local building department first

Why This Is the Correct Answer

Michigan's Michigan Occupational Code and residential construction statutes require change orders to be in writing and signed by both parties to be legally enforceable. This requirement applies regardless of the dollar amount, protecting both homeowners and contractors from misunderstandings.

Why the Other Options Are Wrong

Option A: Notarized if over 10% of original contract value

Michigan law does not require notarization of change orders at any threshold. Notarization is a distractor. The law simply requires written form and mutual signatures.

Option C: Verbal agreements are sufficient if under $5,000

Verbal agreements for change orders are not legally sufficient in Michigan regardless of the amount. This is a common misconception β€” even a $500 change should be documented in writing.

Option D: Approved by the local building department first

Building department approval is required for certain work (permits), but it is a separate process from the contractual change order between contractor and homeowner. Approval from the department does not substitute for a signed change order.

Memory Technique

Change = Change in writing. If anything CHANGES about the contract, it must be WRITTEN and SIGNED by BOTH parties. Think: no paper, no promise.

Was this explanation helpful?

More Michigan Questions

A residential foundation wall in Michigan is 8 feet high with 2 feet above grade. The backfill exerts lateral pressure of 30 psf per foot of depth. What is the maximum lateral pressure at the bottom of the foundation wall?

A builder discovers that the electrical service entrance was installed without proper permits. According to Michigan law, what is the most appropriate next step?

What is the maximum allowable span for a 2x8 floor joist (Grade 2 Douglas Fir) at 16" O.C. with 40 psf live load and 10 psf dead load according to Michigan Building Code span tables?

According to Michigan Building Code, what is the maximum height of a wood-framed bearing wall using 2x4 studs with standard construction?

A homeowner requests to convert a bedroom into a bathroom on the second floor. What is the primary Michigan code concern the builder must address?

According to Michigan plumbing regulations, what is the minimum pipe size required for a water service line serving a single-family residence?

A contractor is building a basement foundation wall that is 8 feet high and will retain 6 feet of soil. What is the minimum wall thickness required by the Michigan Building Code for poured concrete?

A homeowner wants to install a gas fireplace in their living room. The contractor notices the existing gas line is 1/2 inch black iron pipe. For a 40,000 BTU fireplace with a 25-foot run, is this pipe size adequate according to Michigan gas code?

During a framing inspection, the building official notes that the contractor used 2x4 studs at 24 inches on center for an exterior wall. According to Michigan Building Code, what is the maximum wall height allowed for this configuration?

A contractor is installing a beam to support floor joists. The beam must carry a total load of 8,000 pounds over a 12-foot span. If the allowable fiber stress for the lumber grade is 1,200 psi, what is the minimum required section modulus?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.