A contractor submits a progress payment request for $8,500 on a public works project. The public agency has how many days to pay after receiving a proper payment request?
Correct Answer
D) 30 days
Public agencies must pay progress payments within 30 days of receiving a proper payment request under California prompt payment law.
Why This Is the Correct Answer
California's prompt payment law requires public agencies to pay progress payment requests within 30 days of receiving a proper and undisputed payment request. This applies to public works projects and ensures contractors receive timely payment for completed work.
Why the Other Options Are Wrong
Option A: 45 days
45 days is not the correct timeframe for public agency progress payments. While some payment timelines in construction law extend to 45 days, the standard for public agency progress payments is 30 days under California prompt payment statutes.
Option B: 21 days
21 days is not a standard payment window in California public works prompt payment law. This figure does not correspond to the statutory requirement for public agency progress payments.
Option C: 15 days
15 days is too short and not the required payment window for public agency progress payments. The 15-day figure may appear in other contexts but is not the deadline for public agency payment of progress claims.
Memory Technique
Public agencies get 30 days β think of it as a full month to process and pay. '30 days for public pays.' If a private owner gets fewer days in some contexts, public agencies get the standard 30.
More California Questions
A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?
A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?
Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?
A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?
Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?
Which of the following contracts is NOT subject to the 3-day right to cancel under California law?
A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?
A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?
A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?
A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
