A contractor submits a progress payment application on the 5th of the month. Under prompt payment requirements, what is the latest date the owner must pay without incurring interest penalties?

Correct Answer

A) 35th day from submission

California prompt payment law generally requires payment within 30 days, with interest accruing after that period. Some contracts may specify different terms, but 30-35 days is typical.

Answer Options
A
35th day from submission
B
15th of the month
C
25th of the month
D
20th of the month

Why This Is the Correct Answer

California's prompt payment law (Business & Professions Code §7108.5 and Civil Code §8800 et seq.) requires owners to pay contractors within 30 days of receiving a proper pay application. Submitted on the 5th, day 30 lands on the 35th of that month (i.e., the 4th of the following month). Payment on or before that date avoids interest penalties, which accrue at 2% per month on the unpaid balance.

Why the Other Options Are Wrong

Option B: 15th of the month

The 15th of the month is only 10 days after submission—far shorter than the 30-day window California law provides. This deadline would apply only if the contract specifically shortened the payment period, which is unusual and still must meet statutory minimums.

Option C: 25th of the month

The 25th of the month represents 20 days after submission. While some contracts set a 20-day schedule, the statutory default under California prompt payment law is 30 days, making the 25th too early to be the legal deadline.

Option D: 20th of the month

The 20th is only 15 days from submission. This timeframe is too short to satisfy the 30-day statutory requirement and has no basis in California prompt payment statutes for standard progress payment applications.

Memory Technique

Think 'thirty days hath the owner' — just like the rhyme for days in a month. Submit on day 5, count 30 days forward, that is day 35 (or the 4th of the next month). The number 30 is your anchor for California prompt payment.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.