A contractor submits a progress payment application for $12,000 on a public works project. Under California prompt payment law, within how many days must the public entity pay or provide written notice of disputed amounts?

Correct Answer

A) 30 days

California prompt payment law requires public entities to pay undisputed progress payments within 30 days.

Answer Options
A
30 days
B
15 days
C
60 days
D
45 days

Why This Is the Correct Answer

California's prompt payment law (Public Contract Code §20104.50) requires public entities to pay undisputed progress payment applications within 30 days of receipt, or to provide written notice of any disputed amounts within that same period. Failure to pay within 30 days triggers penalty interest on the unpaid amount.

Why the Other Options Are Wrong

Option B: 15 days

15 days is incorrect. While some private project prompt payment rules involve shorter windows for certain sub-tiers, the public entity standard for progress payments is 30 days, not 15.

Option C: 60 days

60 days is incorrect and would give public entities an unreasonably long time to process payment applications. The 30-day rule exists precisely to prevent government agencies from using extended payment delays to manage cash flow at contractors' expense.

Option D: 45 days

45 days is incorrect. 45 days is not a threshold recognized under California's public works prompt payment statute. This is a common distractor that falls between the correct answer (30 days) and the incorrect 60-day option.

Memory Technique

Public works prompt payment: '30 days = one month.' Think of it as a standard monthly billing cycle. If a government agency hasn't paid or disputed within one calendar month of receiving the payment application, penalty interest starts accruing. '30 days or dispute in writing' is the rule.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.