A contractor renovating a pre-1978 home in Oregon must provide the EPA lead pamphlet to the homeowner at least how many days before starting work?
Correct Answer
A) 3 days
Under Oregon lead-based paint regulations, contractors must provide the EPA lead pamphlet at least 3 days before starting renovation work on pre-1978 homes.
Why This Is the Correct Answer
3 days is correct. Under the EPA Renovation, Repair, and Painting (RRP) Rule — adopted by Oregon — contractors must distribute the EPA's 'Renovate Right' pamphlet to owners and occupants of pre-1978 housing at least 3 days (60 hours) before beginning renovation work. This gives residents time to review the information and prepare.
Why the Other Options Are Wrong
Option B: 7 days
7 days is incorrect. This is a common overestimate. The federal RRP Rule and Oregon regulations set the minimum notice at 3 days, not a full week. Seven days is not a threshold used in lead paint notification requirements.
Option C: 10 days
10 days is incorrect. Ten days significantly exceeds the required 3-day notice period. This number does not appear in the RRP Rule's notification timeline.
Option D: 5 days
5 days is incorrect. Five days is between the correct 3-day minimum and the incorrect 7-day distractor. The regulation specifically states 3 days, not 5.
Memory Technique
Remember: 'Lead in 3' — you need to give the lead pamphlet 3 days before you start. Think of the 3 as the 3 letters in 'RRP' or the 3 in '1978 - 75 = 1903' (just kidding — simply memorize: pamphlet = 3 days).
More Oregon Questions
Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?
An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?
A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?
Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?
A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?
A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.
A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?
What is the minimum experience requirement for obtaining an Oregon CCB contractor license?
A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?
A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A contractor is cited for working without proper workers compensation coverage. The base fine is $1,000. If their payroll for the violation period was $45,000, what is the total penalty?
Next Question
A homeowner hires a contractor for a $35,000 deck project. The contractor demands $20,000 upfront before starting work. Under Oregon residential contractor law, what is the maximum legal down payment?