A contractor receives a complaint filed with the NSCB on March 15th. According to Nevada regulations, by what date must the contractor respond?

Correct Answer

D) April 14th

Contractors have 30 days from receipt of a complaint to respond to the NSCB. March 15th + 30 days = April 14th.

Answer Options
A
March 30th
B
April 4th
C
April 29th
D
April 14th

Why This Is the Correct Answer

Nevada regulations give contractors 30 calendar days from receipt of the complaint to respond to the NSCB. Starting from March 15th and counting 30 days forward: March has 31 days, so 16 days remain in March (March 16–31) plus 14 days in April brings the total to 30 days, landing on April 14th.

Why the Other Options Are Wrong

Option A: March 30th

March 30th is only 15 days after March 15th, which is half the allowed response period. This would be the deadline for a 15-day requirement, not a 30-day requirement.

Option B: April 4th

April 4th is 20 days after March 15th, not 30 days. This does not match any regulatory deadline under Nevada's NSCB complaint process.

Option C: April 29th

April 29th is 45 days after March 15th, which exceeds the 30-day response window. This is not a valid NSCB deadline.

Was this explanation helpful?

More Nevada Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.