EstatePass
NevadaNV B&Lhard100% of exam part

A Class B contractor in Nevada wants to bid on a public works project valued at $750,000. What additional bonding requirement must be met?

Correct Answer

A) Payment and performance bonds equal to 100% of contract value

Nevada public works projects typically require both payment and performance bonds equal to 100% of the contract value for projects over certain thresholds.

Answer Options
A
Payment and performance bonds equal to 100% of contract value
B
No additional bonding required beyond license bond
C
Payment and performance bonds equal to 50% of contract value
D
Only a payment bond equal to 100% of contract value

Why This Is the Correct Answer

Nevada law requires both payment bonds and performance bonds equal to 100% of the contract value for public works projects above certain thresholds. For a $750,000 project, this means the contractor must obtain a payment bond of $750,000 AND a performance bond of $750,000 — ensuring both that subcontractors/suppliers get paid and that the project is completed as specified.

Why the Other Options Are Wrong

Option B: No additional bonding required beyond license bond

Claiming no additional bonding is required beyond the license bond is incorrect. Nevada's public works statutes specifically mandate payment and performance bonds for projects at this scale. The standard contractor license bond alone is insufficient for large public works contracts.

Option C: Payment and performance bonds equal to 50% of contract value

Payment and performance bonds at 50% of contract value do not meet Nevada's public works bonding requirement. The statute requires 100% coverage for both bond types to provide full protection to the public entity, subcontractors, and suppliers.

Option D: Only a payment bond equal to 100% of contract value

A payment bond alone at 100% is insufficient — Nevada requires both a payment bond AND a performance bond, each at 100% of contract value. The performance bond protects the public owner if the contractor defaults; omitting it leaves the project owner exposed.

Memory Technique

For public works, remember 'Both at 100%' — Payment bond (protects subs and suppliers) + Performance bond (protects the owner) = double coverage at full value. Think: 'Public money demands full protection — both bonds, full amount.'

Was this explanation helpful?

More Nevada Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.