A contractor performs $12,000 worth of roofing work and files a mechanic's lien for non-payment. Under A.R.S. 33-981, within how many days must the lien be recorded after completion of work?

Correct Answer

A) 120 days

Arizona lien law requires mechanic's liens to be recorded within 120 days of completion of work to be valid.

Answer Options
A
120 days
B
180 days
C
90 days
D
60 days

Why This Is the Correct Answer

Under A.R.S. 33-981, a contractor must record a mechanic's lien within 120 days after the last day of performing work or furnishing materials. Missing this deadline invalidates the lien, leaving the contractor without this powerful collection tool.

Why the Other Options Are Wrong

Option B: 180 days

180 days is too long. This figure may be confused with other legal deadlines (such as some notice of claim periods) but is not the Arizona mechanic's lien recording deadline.

Option C: 90 days

90 days is the deadline used in many other states and is a common wrong answer for Arizona-specific questions. Arizona allows a more generous 120-day window.

Option D: 60 days

60 days is too short and would cause many contractors to lose lien rights prematurely. This figure appears in some preliminary notice deadlines but not in the lien recording requirement.

Memory Technique

Arizona lien = 120 days. Think '4 months / 120 days' β€” Arizona gives you a full season (4 months) to file your lien after finishing work. No other common lien deadline is 4 months.

Was this explanation helpful?

More Arizona Questions

What is the current minimum bond amount required for a residential contractor license in Arizona?

A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?

Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?

Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?

A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?

A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?

According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?

A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?

A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?

A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.