A contractor discovers that a preliminary 20-day notice was not properly served on a commercial project in Arizona. The project owner owes $45,000 and the general contractor owes $28,000. What is the maximum amount the contractor can recover through a mechanics' lien?

Correct Answer

B) $0 - no lien rights without proper notice

Under A.R.S. 33-981, proper service of the preliminary 20-day notice is a prerequisite for lien rights. Without proper notice, no mechanics' lien can be filed.

Answer Options
A
$28,000 - limited to amount owed by general contractor
B
$0 - no lien rights without proper notice
C
$45,000 - full amount owed by owner
D
$73,000 - total of both amounts

Why This Is the Correct Answer

Under A.R.S. § 33-981, serving the preliminary 20-day notice is a jurisdictional prerequisite to establishing lien rights in Arizona. Without proper service, the subcontractor or material supplier has no lien rights whatsoever — regardless of the amounts owed. The preliminary notice is not optional; it is the foundation of the entire lien claim. Failure to properly serve it results in a complete forfeiture of lien rights.

Why the Other Options Are Wrong

Option A: $28,000 - limited to amount owed by general contractor

$28,000 incorrectly assumes the contractor retains some lien rights limited to what the GC owes. No lien rights exist at all without proper preliminary notice — the amount owed by the GC is irrelevant.

Option C: $45,000 - full amount owed by owner

$45,000 incorrectly assumes the contractor can lien for the full owner-owed amount. Even if the owner received value from the work, the contractor's failure to serve the preliminary notice eliminates all lien rights regardless of what the owner owes.

Option D: $73,000 - total of both amounts

$73,000 incorrectly totals both amounts and assumes complete lien rights. This would only be relevant if proper preliminary notice had been served and both amounts were within the allowable lien period.

Memory Technique

The preliminary 20-day notice is the KEY that unlocks the lien door. No key = no entry, no matter how much you're owed. Think: 'No notice, no lien — $0, every time.' This is a bright-line rule with no exceptions in Arizona.

Was this explanation helpful?

More Arizona Questions

What is the current minimum bond amount required for a residential contractor license in Arizona?

A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?

Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?

Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?

A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?

A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?

According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?

A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?

A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?

A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.