EstatePass
OregonOR B&Lmedium100% of exam part

A contractor is renovating a 1972 Oregon duplex and will disturb 45 square feet of painted trim. Which statement about lead-safe work practices is correct?

Correct Answer

B) Must contain work area and use HEPA vacuum

Work in pre-1978 housing disturbing more than 6 sq ft requires full RRP compliance including containment, HEPA vacuum, and certified renovator supervision.

Answer Options
A
Can use standard plastic sheeting for containment
B
Must contain work area and use HEPA vacuum
C
No special precautions required due to small area
D
Only need to wet surfaces before scraping

Why This Is the Correct Answer

The correct answer is B (must contain work area and use HEPA vacuum). The EPA's Renovation, Repair, and Painting (RRP) Rule applies to pre-1978 housing when more than 6 square feet of painted surface is disturbed indoors. A 1972 duplex predates 1978, and 45 sq ft exceeds the 6 sq ft threshold, triggering full RRP compliance: work area containment, HEPA vacuuming, and certified renovator supervision.

Why the Other Options Are Wrong

Option A: Can use standard plastic sheeting for containment

Standard plastic sheeting alone is insufficient. RRP rules require a specific containment protocol β€” not just any plastic sheeting. The work area must be properly sealed to prevent dust migration, and HEPA vacuuming is also required.

Option C: No special precautions required due to small area

No special precautions required is incorrect and dangerous. The small area exemption only applies when less than 6 square feet of painted surface is disturbed indoors. At 45 square feet, full RRP compliance is mandatory.

Option D: Only need to wet surfaces before scraping

Wetting surfaces before scraping alone is insufficient. While wetting is a component of some lead-safe practices, it does not satisfy RRP compliance requirements on its own. Containment and HEPA vacuuming are also required.

Memory Technique

Remember the RRP triggers: Pre-1978 housing + more than 6 sq ft interior (or 20 sq ft exterior) = full RRP compliance required. Think '6 square feet = lead-safe mandate kicks in.' HEPA + contain = the two must-dos.

Was this explanation helpful?

More Oregon Questions

Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?

An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?

A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?

Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?

A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?

A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.

A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?

What is the minimum experience requirement for obtaining an Oregon CCB contractor license?

A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?

A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.