MichiganBuildermedium50% of exam part

A contractor is pouring a concrete footing that is 20 inches wide, 10 inches thick, and 40 feet long. How many cubic yards of concrete are needed?

Correct Answer

D) 2.47 cubic yards

Volume = (20/12) × (10/12) × 40 = 1.67 × 0.83 × 40 = 55.6 cubic feet. Convert to yards: 55.6 ÷ 27 = 2.06 cubic yards. Adding 20% waste factor: 2.06 × 1.2 = 2.47 cubic yards.

Answer Options
A
3.21 cubic yards
B
4.15 cubic yards
C
2.06 cubic yards
D
2.47 cubic yards

Why This Is the Correct Answer

Convert all dimensions to feet: 20 in = 1.667 ft, 10 in = 0.833 ft. Volume = 1.667 × 0.833 × 40 = 55.56 cu ft. Convert to cubic yards: 55.56 ÷ 27 = 2.057 cu yd. Apply 20% waste factor: 2.057 × 1.20 = 2.47 cubic yards, which matches option D.

Why the Other Options Are Wrong

Option A: 3.21 cubic yards

3.21 cubic yards is significantly over the correct amount. This figure might result from applying an incorrect waste factor (e.g., 56%) or using the wrong unit conversion — for example, forgetting to divide by 27 and instead dividing by a smaller number.

Option B: 4.15 cubic yards

4.15 cubic yards is too high. It may stem from not converting inches to feet before multiplying, keeping the width and thickness in inches and then dividing by 27, which overstates the raw volume.

Option C: 2.06 cubic yards

2.06 cubic yards is the net volume before the waste factor is applied. A common error is to stop the calculation here and neglect to add the 20% waste allowance that contractors must order to account for spillage, consolidation, and over-excavation.

Memory Technique

Use the formula W × T × L ÷ 27 × (1 + waste%). For footings, a 20% waste factor is a common exam assumption. Write out units: (in ÷ 12) to get feet, then feet × feet × feet = cubic feet, ÷ 27 = cubic yards.

Was this explanation helpful?

More Michigan Questions

A residential foundation wall in Michigan is 8 feet high with 2 feet above grade. The backfill exerts lateral pressure of 30 psf per foot of depth. What is the maximum lateral pressure at the bottom of the foundation wall?

A builder discovers that the electrical service entrance was installed without proper permits. According to Michigan law, what is the most appropriate next step?

What is the maximum allowable span for a 2x8 floor joist (Grade 2 Douglas Fir) at 16" O.C. with 40 psf live load and 10 psf dead load according to Michigan Building Code span tables?

According to Michigan Building Code, what is the maximum height of a wood-framed bearing wall using 2x4 studs with standard construction?

A homeowner requests to convert a bedroom into a bathroom on the second floor. What is the primary Michigan code concern the builder must address?

According to Michigan plumbing regulations, what is the minimum pipe size required for a water service line serving a single-family residence?

A contractor is building a basement foundation wall that is 8 feet high and will retain 6 feet of soil. What is the minimum wall thickness required by the Michigan Building Code for poured concrete?

A homeowner wants to install a gas fireplace in their living room. The contractor notices the existing gas line is 1/2 inch black iron pipe. For a 40,000 BTU fireplace with a 25-foot run, is this pipe size adequate according to Michigan gas code?

During a framing inspection, the building official notes that the contractor used 2x4 studs at 24 inches on center for an exterior wall. According to Michigan Building Code, what is the maximum wall height allowed for this configuration?

A contractor is installing a beam to support floor joists. The beam must carry a total load of 8,000 pounds over a 12-foot span. If the allowable fiber stress for the lumber grade is 1,200 psi, what is the minimum required section modulus?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.