A contractor is installing insulation in a cathedral ceiling. According to Michigan Energy Code, what is the minimum R-value required for this application in Climate Zone 6?

Correct Answer

B) R-49

Michigan Energy Code requires R-49 insulation for cathedral ceilings in Climate Zone 6 to meet energy efficiency standards.

Answer Options
A
R-60
B
R-49
C
R-30
D
R-38

Why This Is the Correct Answer

Michigan is in IECC Climate Zone 6 (cold climate). The Michigan Energy Code adopts IECC requirements, which mandate R-49 for cathedral ceilings (unvented or vented roof assemblies with continuous insulation or full-cavity fill) in Climate Zone 6. Cathedral ceilings are more thermally demanding than flat attic assemblies because they lack the large air buffer of a traditional attic, making high R-values critical for energy performance.

Why the Other Options Are Wrong

Option A: R-60

R-60 is the requirement for standard attic assemblies (blown-in insulation with large attic space) in Climate Zone 7, not for cathedral ceilings in Zone 6. This is a common mix-up between attic and cathedral ceiling requirements or between climate zones.

Option C: R-30

R-30 is insufficient for Climate Zone 6 and corresponds to wall assemblies or climate zones with more moderate winters (Zone 3-4). Using R-30 in a Michigan cathedral ceiling would fail energy code inspection.

Option D: R-38

R-38 applies to ceiling assemblies in Climate Zone 5 or to certain wall assemblies. It is below the required R-49 for cathedral ceilings in Michigan's Climate Zone 6 and would not meet code.

Memory Technique

Michigan Zone 6, Cathedral = R-49. Think '49ers' for the cathedral ceiling in cold Michigan. Attic is R-60 (more room for insulation); cathedral is R-49 (limited by rafter depth).

Was this explanation helpful?

More Michigan Questions

A residential foundation wall in Michigan is 8 feet high with 2 feet above grade. The backfill exerts lateral pressure of 30 psf per foot of depth. What is the maximum lateral pressure at the bottom of the foundation wall?

A builder discovers that the electrical service entrance was installed without proper permits. According to Michigan law, what is the most appropriate next step?

What is the maximum allowable span for a 2x8 floor joist (Grade 2 Douglas Fir) at 16" O.C. with 40 psf live load and 10 psf dead load according to Michigan Building Code span tables?

According to Michigan Building Code, what is the maximum height of a wood-framed bearing wall using 2x4 studs with standard construction?

A homeowner requests to convert a bedroom into a bathroom on the second floor. What is the primary Michigan code concern the builder must address?

According to Michigan plumbing regulations, what is the minimum pipe size required for a water service line serving a single-family residence?

A contractor is building a basement foundation wall that is 8 feet high and will retain 6 feet of soil. What is the minimum wall thickness required by the Michigan Building Code for poured concrete?

A homeowner wants to install a gas fireplace in their living room. The contractor notices the existing gas line is 1/2 inch black iron pipe. For a 40,000 BTU fireplace with a 25-foot run, is this pipe size adequate according to Michigan gas code?

During a framing inspection, the building official notes that the contractor used 2x4 studs at 24 inches on center for an exterior wall. According to Michigan Building Code, what is the maximum wall height allowed for this configuration?

A contractor is installing a beam to support floor joists. The beam must carry a total load of 8,000 pounds over a 12-foot span. If the allowable fiber stress for the lumber grade is 1,200 psi, what is the minimum required section modulus?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.