A contractor is building a house near a Louisiana wetland. The project requires disturbing 0.8 acres of land. What federal and state permits are likely required?
Correct Answer
C) Both LDEQ and Corps permits
Projects near wetlands typically require both Louisiana Department of Environmental Quality (LDEQ) permits and U.S. Army Corps of Engineers permits, regardless of acreage.
Why This Is the Correct Answer
Projects near wetlands require both LDEQ (Louisiana Department of Environmental Quality) permits for state environmental compliance and U.S. Army Corps of Engineers permits under Section 404 of the Clean Water Act. Both permits are required regardless of acreage because wetland proximity — not land area alone — triggers the dual-permit requirement.
Why the Other Options Are Wrong
Option A: No permits required for less than 1 acre
The claim that no permits are required for less than 1 acre is incorrect. While the EPA's stormwater NPDES permit has a 1-acre threshold for land disturbance, wetland-specific permits from both LDEQ and the Corps of Engineers are triggered by proximity to and disturbance of wetlands, not by a 1-acre minimum.
Option B: Only state LDEQ permit
Only a state LDEQ permit is insufficient. Federal jurisdiction over navigable waters and wetlands under the Clean Water Act requires an Army Corps of Engineers Section 404 permit for any discharge of fill material into waters of the United States, including wetlands.
Option D: Only federal Corps of Engineers permit
Only a federal Corps of Engineers permit is insufficient. Louisiana also requires state-level LDEQ approval for activities affecting state water quality, operating independently from (but in parallel with) the federal permitting process.
Memory Technique
Wetlands = Double Permits: State (LDEQ) + Federal (Corps of Engineers). Think 'Two Agencies, Two Permits' for any wetland work. The 1-acre rule applies to stormwater, NOT wetland permits.
More Louisiana Questions
A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?
A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?
A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?
Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?
A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?
Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?
Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?
A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?
A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?
A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?