EstatePass
OregonOR B&Lmedium100% of exam part

A contractor files a construction lien on a residential property in Oregon. Under ORS 87, within how many days must the lien be recorded after the last day of work?

Correct Answer

C) 75 days

Under ORS 87, construction liens on residential property must be recorded within 75 days after the last day work was performed.

Answer Options
A
30 days
B
90 days
C
75 days
D
60 days

Why This Is the Correct Answer

The correct answer is C (75 days). ORS 87.035 specifies that a contractor must record a claim of lien within 75 days after the last day labor or materials were furnished on a residential property. This is a firm statutory deadline — missing it extinguishes lien rights.

Why the Other Options Are Wrong

Option A: 30 days

30 days is incorrect. There is no 30-day lien recording deadline for contractors in Oregon. This figure may be confused with preliminary notice deadlines in other states or other notice requirements.

Option B: 90 days

90 days is incorrect. While 90 days is the deadline applicable to commercial/non-residential property liens under ORS 87, it does not apply to residential property liens.

Option D: 60 days

60 days is incorrect. This is a common distractor that falls between the residential (75-day) and shorter deadlines. No Oregon statute sets 60 days as the residential lien recording deadline.

Memory Technique

Think '75 for residential' — a house has 4 walls and a roof, roughly 75 feet around a small lot. Or: '75 days to file or your lien dies.' Residential = 75; Commercial = 90.

Was this explanation helpful?

More Oregon Questions

Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?

An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?

A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?

Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?

A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?

A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.

A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?

What is the minimum experience requirement for obtaining an Oregon CCB contractor license?

A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?

A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.