North CarolinaNC Supplementhard100% of exam part

A contractor discovers underground storage tanks during excavation for a commercial foundation in North Carolina. What is the required first step under NC environmental regulations?

Correct Answer

C) Immediately stop work and notify the NC Department of Environmental Quality

NC environmental regulations require immediate work stoppage and notification of the NC Department of Environmental Quality when underground storage tanks are discovered.

Answer Options
A
Cover the tanks and proceed with construction
B
Continue work and report after project completion
C
Immediately stop work and notify the NC Department of Environmental Quality
D
Remove the tanks and dispose of them in regular waste

Why This Is the Correct Answer

North Carolina environmental regulations require an immediate work stoppage and notification to the NC Department of Environmental Quality (DEQ) upon discovery of underground storage tanks. USTs may contain hazardous substances, and any disturbance without regulatory oversight could cause contamination, create liability, and endanger workers. The DEQ must assess the situation before work can resume.

Why the Other Options Are Wrong

Option A: Cover the tanks and proceed with construction

Covering the tanks and proceeding with construction is incorrect and dangerous. Concealing discovered USTs violates environmental law, can create severe contamination liability, and puts workers and the public at risk. This choice also fails to fulfill the mandatory reporting obligation.

Option B: Continue work and report after project completion

Continuing work and reporting after project completion is incorrect. Delayed reporting after project completion would be a serious violation of NC environmental law. USTs must be reported immediately upon discovery β€” waiting until the project ends could result in criminal and civil liability for contamination.

Option D: Remove the tanks and dispose of them in regular waste

Removing the tanks and disposing of them in regular waste is incorrect and illegal. USTs and their contents are classified as hazardous materials. Unauthorized removal and disposal in regular waste violates federal and state environmental regulations and can result in major fines and criminal charges.

Memory Technique

UST = Unexpected Stop Time. When you find underground storage tanks, the first thing you do is STOP and CALL (NC DEQ). Think: Stop Everything, Call DEQ β€” SEC. Never cover, never continue, never self-remove.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.