EstatePass
CaliforniaContractsmedium20% of exam part

A contractor completes foundation work worth $18,000 on June 1st. The general contractor stops payment on June 20th due to a dispute with the owner. When must the contractor record a mechanics lien to preserve lien rights?

Correct Answer

C) August 30th

The 90-day mechanics lien deadline runs from completion of the work of improvement (June 1st), making the deadline August 30th.

Answer Options
A
November 17th
B
September 19th
C
August 30th
D
August 19th

Why This Is the Correct Answer

Under California Civil Code Section 8412, a claimant who is not the direct contractor (i.e., a subcontractor) must record a mechanics lien within 90 days after completion of the work of improvement. The work was completed June 1st, and 90 days later is August 30th. The payment dispute on June 20th does not restart the clock — the deadline runs from completion of work.

Why the Other Options Are Wrong

Option A: November 17th

November 17th is far beyond the 90-day statutory deadline and would result in loss of lien rights. This date may reflect a miscalculation using a different starting point or a longer timeframe.

Option B: September 19th

September 19th exceeds the 90-day window from June 1st. It may reflect a 110-day calculation or confusion with the direct contractor's deadline. Subcontractors have 90 days from completion of work — not 109 or 110 days.

Option D: August 19th

August 19th would be 79 days from June 1st — short of the 90-day window. While filing earlier is always safer, this date reflects a miscalculation of the actual deadline.

Memory Technique

The lien clock starts when the WORK ends, not when the MONEY stops. Count 90 days from June 1st: June has 30 days (29 remaining after June 1st) + July (31) + August (31) = 91 — land on August 30th.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.