EstatePass
CaliforniaContractshard20% of exam part

A contractor completes a $12,000 bathroom remodel on June 1st. No preliminary notice was served. What is the deadline to file a mechanics lien?

Correct Answer

D) August 30th

Even without a preliminary notice, the contractor has 90 days from completion (June 1st) to file a mechanics lien, making the deadline August 30th. However, the lien amount may be limited without proper notice.

Answer Options
A
July 1st
B
July 31st
C
Cannot file lien without preliminary notice
D
August 30th

Why This Is the Correct Answer

Under California Civil Code Section 8412, a direct contractor has 90 days from completion of the work (or from the date a notice of completion or cessation is recorded) to record a mechanics lien. Counting 90 days from June 1st lands on August 30th. Critically, direct contractors are exempt from the preliminary notice requirement — they can still file a mechanics lien even without serving a preliminary notice, though the lien amount may be affected in some circumstances.

Why the Other Options Are Wrong

Option A: July 1st

July 1st is only 30 days after June 1st — far too early to be the deadline, and 30 days is not a standard mechanics lien recording deadline for direct contractors on private projects.

Option B: July 31st

July 31st is 60 days after June 1st, which corresponds to the deadline for subcontractors and material suppliers when a notice of completion has been recorded — not for direct contractors, and not in this scenario where no notice of completion is mentioned.

Option C: Cannot file lien without preliminary notice

This is a dangerous distractor. Direct contractors are explicitly exempt from the preliminary notice requirement under Civil Code Section 8200. Failing to serve a preliminary notice does not bar a direct contractor from recording a mechanics lien. Subcontractors and suppliers lose lien rights without preliminary notice, but not direct contractors.

Memory Technique

90 days = 3 months = roughly the end of the third month after completion. June 1 + 3 months = September 1, but subtract a day for the 90-day count = August 30th. Visualize a summer construction project: finish in June, lien deadline hits just before summer ends.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.