epa-608-type-3Purge Units & Leak Controlmedium

A leak has been found on a large low-pressure chiller that falls under the leak repair provisions. Within what period does the rule expect that leak to be repaired?

Correct Answer

C) Within thirty days of the date the leak was found by the servicing technician

Once a leak has been identified on an appliance covered by the leak repair provisions, the clock starts on the day of discovery and the owner has thirty days to complete the repair. Extensions exist for specific situations, such as equipment that has to be shut down at a time of year the plant cannot manage, but the base period is thirty days. Nothing in the rule allows a leak to be logged and left until the next season.

Answer Options
A
Within seven days of the date the leak was found by the servicing technician
B
Within ninety days of the date the leak was found by the servicing technician
C
Within thirty days of the date the leak was found by the servicing technician
D
Within one year of the date the leak was found by the servicing technician

Why This Is the Correct Answer

The repair period runs from the date the leak is discovered, and it is thirty days. That period is short on purpose, because refrigerant continues to escape and moisture continues to enter for as long as the leak is open. The owner is the party responsible for meeting it, and the dates of discovery and repair both go into the service record.

Why the Other Options Are Wrong

Option A: Within seven days of the date the leak was found by the servicing technician

A week would be unworkable for equipment that often has to be scheduled around a plant's load, and no such period appears in the rule.

Option B: Within ninety days of the date the leak was found by the servicing technician

Ninety days is far longer than the rule allows and would let a chiller lose a large share of its charge before anyone acted.

Option D: Within one year of the date the leak was found by the servicing technician

A year is roughly a full cooling season. Allowing that would defeat the purpose of having leak repair provisions at all.

Memory Technique

One month to fix it. Thirty days from the day you found it, not the day you got around to it.

Reference Hint

Leaks on appliances covered by the leak repair provisions must be repaired within thirty days of discovery.

Was this explanation helpful?

More epa-608-type-3 Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.