The original contractor receives retention that includes a subcontractor's share. When should the original contractor pass the subcontractor's share if no allowed withholding applies?
Correct Answer
B) Within 7 days after receiving the retention payment.
Public Contract Code Section 7107 generally requires the original contractor to pay the subcontractor's share of retention within 7 days after receipt.
Why This Is the Correct Answer
Public Contract Code Section 7107 generally requires the original contractor to pay the subcontractor's share of retention within 7 days after receipt.
Why the Other Options Are Wrong
Option A: Within 60 days after receiving the first bid.
Within 60 days after receiving the first bid. skips the written authority, scope, price, notice, or release control needed for subcontractor retention.
Option C: Only after the public entity renews the contractor's license.
Only after the public entity renews the contractor's license. skips the written authority, scope, price, notice, or release control needed for subcontractor retention.
Option D: Use the agency standard retention percentage without checking the statutory cap or exception.
Use the agency standard retention percentage without checking the statutory cap or exception. skips the written authority, scope, price, notice, or release control needed for subcontractor retention.
Memory Technique
When public clashes with contract, let the contract speak before Paying Agency.
Reference Hint
Study anchor (closed-book): memorize Subcontractor retention from California Code, Public Contract Code Sections 7107 and 7201. / California Code, Public Contract Code Section 7107; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
