After a progress check has cleared, what document should replace the earlier conditional release for that paid portion?
Correct Answer
B) A signed unconditional waiver and release for the paid portion.
After payment, CSLB guidance points to an unconditional release signed by the claimant for the portion paid.
Why This Is the Correct Answer
After payment, CSLB guidance points to an unconditional release signed by the claimant for the portion paid.
Why the Other Options Are Wrong
Option A: A new bid proposal from the same subcontractor.
A new bid proposal from the same subcontractor. skips the written authority, scope, price, notice, or release control needed for lien releases.
Option C: A reminder email that the owner intends to pay later.
A reminder email that the owner intends to pay later. skips the written authority, scope, price, notice, or release control needed for lien releases.
Option D: A supplier catalog page showing the material was available, because the material was available from that supplier.
A supplier catalog page showing the material was available, because the material was available from that supplier. skips the written authority, scope, price, notice, or release control needed for lien releases.
Memory Technique
Closing Paperwork shortcut is not a term until paper carries it.
Reference Hint
Study anchor (closed-book): memorize Lien releases from CSLB Mechanics Lien guidance; California Civil Code / California Civil Code conditional and unconditional waiver and release forms; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
