A subcontractor performed extra work after a superintendent gave a verbal field direction, but the owner never signed a change order. What should the prime avoid?
Correct Answer
C) Billing the owner as though a signed change order already exists.
For CA home improvement contracts, owner price or scope changes should be handled by a signed written change order before the change becomes part of the contract.
Why This Is the Correct Answer
For CA home improvement contracts, owner price or scope changes should be handled by a signed written change order before the change becomes part of the contract.
Why the Other Options Are Wrong
Option A: Reviewing the subcontract and daily reports.
Reviewing the subcontract and daily reports. skips the written authority, scope, price, notice, or release control needed for project contracts.
Option B: Determining who authorized the field direction.
Determining who authorized the field direction. skips the written authority, scope, price, notice, or release control needed for project contracts.
Option D: Documenting the dispute before negotiating responsibility, before deciding whether owner approval was actually obtained.
Documenting the dispute before negotiating responsibility, before deciding whether owner approval was actually obtained. skips the written authority, scope, price, notice, or release control needed for project contracts.
Memory Technique
When home clashes with improvement, let the contract speak before Handling Disputed.
Reference Hint
Study anchor (closed-book): memorize Project contracts from CSLB 2026 Law Book; CSLB Home Improvement Contracts / Business and Professions Code Section 7159; know the rule or calculation trigger without relying on exam-room lookup.
More Law & Business Questions
A Fresno homeowner wants a $725 cabinet repair and trim adjustment. Which contract step best matches CA home improvement requirements?
A project has $6,500 retainage withheld. The owner releases 60 percent of retainage at substantial completion. How much cash is released?
Cash is $52,500 and monthly burn is $17,500. How many months of runway are available?
A supplier offers 1.5 percent early-pay discount on a $22,000 invoice. What is the discount?
A balance sheet lists assets of $310,000 and liabilities of $185,000. What is owner's equity?
A job is estimated to cost $135,000. What price gives a 25 percent gross margin?
A customer invoice of $4,000 has a stated late charge of 1.5 percent. What late charge is added?
A bid has direct labor of $18,000, materials of $12,500, and equipment rental of $3,500. If the contractor adds 20 percent markup on direct cost, what is the bid price?
A contractor wants a 25 percent gross margin on a job with estimated cost of $60,000. What selling price gives that margin?
A completed project sold for $150,000 and had total cost of $126,000. What gross margin percentage did the project earn?
