Stored drywall sheets lean into a hallway used as the site's emergency route. What should be corrected?
Correct Answer
A) Blocked egress.
Move and safely store the sheets so the required route remains clear. Section 1513(c) addresses dangerous obstructions in construction walkways. Source: https://www.dir.ca.gov/title8/1513.html
Why This Is the Correct Answer
Move and safely store the sheets so the required route remains clear. Section 1513(c) addresses dangerous obstructions in construction walkways. Source: https://www.dir.ca.gov/title8/1513.html
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Class B Trade Questions
An attic furnace platform blocks required access to service panels. What should be maintained?
A panel edge called out for blocking in the structural notes is left unsupported. What should be installed?
A new dwelling laundry area has a 125-volt, 20-ampere receptacle supplied by a 120-volt single-phase circuit, without required personnel ground-fault interruption. Which protection is missing?
Which listed hazard is directly increased by carrying a forklift load high while traveling through a doorway?
A penetration through a rated gypsum wall is patched with ordinary joint compound only. What must be maintained?
A shear wall panel is installed but the specified edge nailing is missing at panel edges. What is the issue?
A service panel is installed where stored material blocks the working area. What must be maintained?
A fire-rated wall patch is finished with standard materials without matching the tested assembly. What must be preserved?
A joist hanger is installed with drywall screws instead of the fasteners specified by the hardware manufacturer. What should be corrected?
A field change includes 28 added labor-hours at $69 per hour plus $880 in material. What direct cost should be priced before markup?
People Also Study
Related Study Resources
Previous Question
Fresh concrete is placed against absorbent forms in hot weather without pre-wetting or curing planning. What is the concern?
Next Question
The applicable scaffold plan requires a guardrail system at an open side. The platform is complete but that system is missing. What must be installed?
