Fresh concrete is placed against absorbent forms in hot weather without pre-wetting or curing planning. What is the concern?
Correct Answer
C) Moisture loss.
Uncontrolled moisture loss can harm curing and surface quality, especially in hot or dry placement conditions.
Why This Is the Correct Answer
Uncontrolled moisture loss can harm curing and surface quality, especially in hot or dry placement conditions.
More ca-trade-b Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Low-VOC finish material requirements are listed in the project notes, but the submittal does not identify the product category. What should be verified?
Next Question
Concrete is scheduled over expansive soil that has not been prepared as required by the plan. What should be corrected?