Class B TradeFraming & Structuralmedium20% of exam part

A new beam post bears on floor sheathing between joists. The sheathing is not designed for this reaction and no supporting transfer detail is provided. What permanent provision is missing?

Correct Answer

B) Adequate bearing support and a verified permanent load path.

Provide a verified permanent path for the beam reaction to adequate support below. Temporary shoring may be necessary during correction, but does not replace the required permanent load path.

Answer Options
A
Temporary shoring only, with no permanent support correction.
B
Adequate bearing support and a verified permanent load path.
C
Only a fire-rated finish below the post.
D
Only a thicker floor covering above the sheathing.

Why This Is the Correct Answer

Provide a verified permanent path for the beam reaction to adequate support below. Temporary shoring may be necessary during correction, but does not replace the required permanent load path.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Class B Trade Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.