A wall panel designated as braced is sheathed with a different panel thickness than the approved plan. What should be done?
Correct Answer
C) Match approved detail.
Braced or shear wall sheathing should match the approved design or an approved revision.
Why This Is the Correct Answer
Braced or shear wall sheathing should match the approved design or an approved revision.
Why the Other Options Are Wrong
Option A: The joist may be structurally weakened.
The joist may be structurally weakened. relies on the wrong note, symbol, sheet, scale, or detail path for braced wall sheathing.
Option B: Truss repair.
Truss repair. relies on the wrong note, symbol, sheet, scale, or detail path for braced wall sheathing.
Option D: Water intrusion at the wall.
Water intrusion at the wall. relies on the wrong note, symbol, sheet, scale, or detail path for braced wall sheathing.
Memory Technique
Braced Wall Sheathing trail for Checking Lateral: note to schedule to detail, then field action.
Reference Hint
Study anchor (closed-book): memorize Braced wall sheathing from California Building Code, California Code of Regulations Title 24. / Title 24 California Building Code braced wall and shear wall sheathing concepts; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?