A long uninterrupted gypsum ceiling omits the control joint shown on the plans. What risk increases?

Correct Answer

C) Random cracking.

A missing planned control joint removes intended stress relief and can increase random cracking. Restore the specified detail; no universal spacing is established by this scenario. Source: https://www.usg.com/api/download-center/v1/assets/b0069f45-3588-538e-acc7-927b5d31bce8?country=us&download=true

Answer Options
A
An automatic increase in fire resistance.
B
An increase in ceiling load capacity.
C
Random cracking.
D
A reduction in the required fastening.

Why This Is the Correct Answer

A missing planned control joint removes intended stress relief and can increase random cracking. Restore the specified detail; no universal spacing is established by this scenario. Source: https://www.usg.com/api/download-center/v1/assets/b0069f45-3588-538e-acc7-927b5d31bce8?country=us&download=true

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Class B Trade Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.