A crew cuts fiber-cement siding indoors without dust controls. What should be coordinated?
Correct Answer
D) Establish and implement an applicable silica-exposure control method.
Stop the uncontrolled cutting and establish an applicable silica-exposure control method. Title 8 section 1532.3 Table 1(iii) limits its fiber-cement handheld-saw dust-collection method to outdoor use. Indoor work needs an applicable Table 1 method with all its conditions, or assessment and controls under subsection (d); do not assume the outdoor-only method applies. Source: https://www.dir.ca.gov/title8/1532_3.html
Why This Is the Correct Answer
Stop the uncontrolled cutting and establish an applicable silica-exposure control method. Title 8 section 1532.3 Table 1(iii) limits its fiber-cement handheld-saw dust-collection method to outdoor use. Indoor work needs an applicable Table 1 method with all its conditions, or assessment and controls under subsection (d); do not assume the outdoor-only method applies. Source: https://www.dir.ca.gov/title8/1532_3.html
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Class B Trade Questions
An attic furnace platform blocks required access to service panels. What should be maintained?
A panel edge called out for blocking in the structural notes is left unsupported. What should be installed?
A new dwelling laundry area has a 125-volt, 20-ampere receptacle supplied by a 120-volt single-phase circuit, without required personnel ground-fault interruption. Which protection is missing?
Which listed hazard is directly increased by carrying a forklift load high while traveling through a doorway?
A penetration through a rated gypsum wall is patched with ordinary joint compound only. What must be maintained?
A shear wall panel is installed but the specified edge nailing is missing at panel edges. What is the issue?
A service panel is installed where stored material blocks the working area. What must be maintained?
A fire-rated wall patch is finished with standard materials without matching the tested assembly. What must be preserved?
A joist hanger is installed with drywall screws instead of the fasteners specified by the hardware manufacturer. What should be corrected?
A field change includes 28 added labor-hours at $69 per hour plus $880 in material. What direct cost should be priced before markup?