A window opening is being flashed with separate sill, jamb, and head pieces. What sequence best supports shingle-lap water management?
Correct Answer
C) Sill flashing first, then jamb flashing, then head flashing integrated at the top.
Sill flashing comes first, then jambs, then head flashing so upper pieces shed over lower pieces.
Why This Is the Correct Answer
Sill flashing comes first, then jambs, then head flashing so upper pieces shed over lower pieces.
Why the Other Options Are Wrong
Option A: Head flashing first, then sill flashing, then jamb flashing.
Head flashing first, then sill flashing, then jamb flashing. addresses a neighboring field issue, but not the condition or method control required for opening flashing.
Option B: Jamb flashing first, then head flashing, with no sill treatment, with no sill treatment under the window frame at all.
Jamb flashing first, then head flashing, with no sill treatment, with no sill treatment under the window frame at all. addresses a neighboring field issue, but not the condition or method control required for opening flashing.
Option D: Install all flashing after siding so it remains visible.
Install all flashing after siding so it remains visible. addresses a neighboring field issue, but not the condition or method control required for opening flashing.
Memory Technique
Opening Flashing method for Observing Window: condition first, tool second.
Reference Hint
Study anchor (closed-book): memorize Opening flashing from 2025 California Building Code and 2025 California Residential Code. / Title 24 California exterior opening flashing and weather protection; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?
