A service calculation is limited to 146 amperes and already includes 96 amperes of noncontinuous load. With the remainder carried at 125 percent, what continuous load can be included?
- 40 amperes
- B50 amperes
- C32 amperes
- D62.5 amperes
Why A is correct
Subtract the noncontinuous load first: 146 − 96 = 50 amperes of calculated allowance. Dividing that allowance by 1.25 gives 40 amperes of actual continuous load.