In August 2026, a contractor framed an addition two feet closer to the side lot line than shown on the approved construction documents. During inspection, the building official noticed the discrepancy. What is the most likely consequence?

Correct Answer

B) The work may have to stop until the construction is corrected or revised approval is obtained

When field construction differs materially from the approved documents, the building official can require correction or revised approval before the work proceeds. A paid permit fee does not lock in acceptance of nonconforming construction.

Answer Options
A
The change must be accepted because the permit fee was already paid
B
The work may have to stop until the construction is corrected or revised approval is obtained
C
The discrepancy automatically becomes lawful once drywall is installed
D
The official must issue a certificate of occupancy if the owner signs a waiver

Why This Is the Correct Answer

Sign up free to unlock full analysis

Why the Other Options Are Wrong

Sign up free to unlock full analysis

Deep Analysis of This Land Use Controls Regulations Question

Sign up free to unlock full analysis

Background Knowledge for Land Use Controls Regulations

Sign up free to unlock full analysis
Sign up free to unlock full analysis

Real World Application in Land Use Controls Regulations

Sign up free to unlock full analysis

Common Mistakes to Avoid on Land Use Controls Regulations Questions

Sign up free to unlock full analysis

Related Topics & Key Terms

Key Terms:

approved_plansinspectionfield_changestop_workbuilding_official
Was this explanation helpful?

More Land Use Controls Regulations Questions

People Also Study

Practice More Questions

Access 2,000+ practice questions and pass your real estate exam.

Start Practicing