EstatePass
Originationmedium27% of exam

During a training quiz scenario, a quality-control reviewer encounters a TILA Loan Estimate Timing issue. Which response should decide how the file should be documented?

Correct Answer

A) Issue a revised Loan Estimate within three business days when valid

Under TILA's Regulation Z, a Loan Estimate must be provided within three business days of receiving a loan application. A revised Loan Estimate can be issued only if specific "valid" changed circumstances occur (e.g., changes in loan terms, property, or settlement charges) that increase the APR beyond a tolerance or affect the borrower's eligibility. When such a valid change happens, the revised Loan Estimate must be provided within three business days of the lender learning of the change. Why this is correct: "Issue a revised Loan Estimate within three business days when valid" correctly states the rule. The timing is mandatory, and the revision is permitted only for legitimate changed circumstances as defined by Regulation Z. Why the other choices are wrong: "Ignore redisclosure timing because the borrower verbally accepted the new terms" is wrong because verbal acceptance does not waive the legal requirement to provide proper written disclosures within the mandated timeframe. "Increase disclosed costs based on an internal pricing preference without file-specific support" is wrong because cost increases must be tied to a valid changed circumstance, not lender preference, to justify a revised estimate. "Use the revised Loan Estimate only to improve pricing after the borrower shops a competitor" is wrong because a revised Loan Estimate cannot be used for strategic re-pricing; it is only for responding to specific, valid changes that affect the transaction. Exam tip: Remember the "three-business-day" rule applies twice: for the initial Loan Estimate after application and for a revised Loan Estimate after a valid changed circumstance.

Answer Options
A
Issue a revised Loan Estimate within three business days when valid
B
Ignore redisclosure timing because the borrower verbally accepted the new terms.
C
Increase disclosed costs based on an internal pricing preference without file-specific support.
D
Use the revised Loan Estimate only to improve pricing after the borrower shops a competitor.

Why This Is the Correct Answer

The correct response is "Issue a revised Loan Estimate within three business days when valid" because Changed circumstances can permit revised estimates only when Regulation Z conditions and timing are met.

Why the Other Options Are Wrong

Option B: Ignore redisclosure timing because the borrower verbally accepted the new terms.

This choice is a tempting shortcut, but it conflicts with changed-circumstance documentation because the file still needs the required documentation, timing, or rule-based review before the action is taken.

Option C: Increase disclosed costs based on an internal pricing preference without file-specific support.

This choice is a tempting shortcut, but it conflicts with changed-circumstance documentation because the file still needs the required documentation, timing, or rule-based review before the action is taken.

Option D: Use the revised Loan Estimate only to improve pricing after the borrower shops a competitor.

This choice is a tempting shortcut, but it conflicts with changed-circumstance documentation because the file still needs the required documentation, timing, or rule-based review before the action is taken.

Memory Technique

changed-circumstance review: identify the rule being tested, then choose the action that documents or applies that rule before the file moves forward.

Exam Tip

For changed-circumstance documentation questions, separate the required file step from plausible sales, timing, or documentation shortcuts.

Common Mistakes to Avoid

  • -Choosing an internal exception instead of the governing rule
  • -Treating preliminary or informal facts as a substitute for required documentation
  • -Answering from a familiar but unrelated mortgage topic
Was this explanation helpful?

More Origination Questions

Before the team acts on a servicing handoff check, a closing coordinator must address Asset Verification and Reserves. Which response is most defensible?

An MLO is reviewing procedures for a case where a cost changes after the Closing Disclosure has already been provided. What is the proper handling?

During a post-application update, a quality-control reviewer encounters a Credit Analysis and Evaluation issue. Which response should avoid a shortcut that would misapply the rule?

A construction-to-permanent loan will disburse in 5 draws over 11 months before the permanent phase begins. Which Regulation Z appendix provides a disclosure method for multiple-advance construction transactions?

Before closing, the team discovers that a borrower asks which upfront charge can be collected before intent to proceed. What is the safest compliant answer?

A construction loan agreement allows advances only after documented completion of specified work. A builder requests the next draw, but no completion evidence has been provided. What should occur?

Before releasing the final construction draw, which combination most directly supports project completion and clear collateral?

A construction-to-permanent loan will convert to a substantially higher fully amortizing payment. Which payment is especially important when assessing the borrower's long-term repayment capacity?

A construction-to-permanent note states that conversion requires completion, a certificate of occupancy, and no unresolved liens. Construction is finished, but a mechanic's lien remains. What should happen?

A branch manager asks about a loan file because a processor wants to omit known monthly obligations from underwriting. What should happen?

People Also Study

Related Study Resources

Practice More MLO Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your SAFE MLO exam.

Start Practicing