EstatePass
Originationeasy27% of exam

A construction-to-permanent note states that conversion requires completion, a certificate of occupancy, and no unresolved liens. Construction is finished, but a mechanic's lien remains. What should happen?

Correct Answer

B) Resolve the lien or satisfy the stated conversion condition before conversion

Why this is correct: The note states conversion requires completion, a certificate of occupancy, and no unresolved liens. If a mechanic's lien remains, the condition "no unresolved liens" is not met. Therefore, you must resolve the lien or satisfy the stated conversion condition before conversion. This protects the lender's first lien position and ensures clear title before the loan converts to its permanent phase. Why the other choices are wrong: The option "Convert because physical completion is the only relevant condition" is incorrect because it ignores the other explicitly stated conditions in the contract. The option "Delete the lien from the lender's records" is wrong; a lien is a legal claim against the property that cannot be removed by simply deleting a record—it must be resolved. The option "Advance additional funds without review" is incorrect; advancing more funds without resolving the existing lien would increase risk and violate prudent lending and the loan agreement. Exam tip: All contractual conversion conditions are conjunctive ('and'); failure of any one prevents conversion.

Answer Options
A
Convert because physical completion is the only relevant condition
B
Resolve the lien or satisfy the stated conversion condition before conversion
C
Delete the lien from the lender's records
D
Advance additional funds without review

Why This Is the Correct Answer

Why this is correct: The note states conversion requires completion, a certificate of occupancy, and no unresolved liens. If a mechanic's lien remains, the condition "no unresolved liens" is not met. Therefore, you must resolve the lien or satisfy the stated conversion condition before conversion. This protects the lender's first lien position and ensures clear title before the loan converts to its permanent phase. Why the other choices are wrong: The option "Convert because physical completion is the only relevant condition" is incorrect because it ignores the other explicitly stated conditions in the contract. The option "Delete the lien from the lender's records" is wrong; a lien is a legal claim against the property that cannot be removed by simply deleting a record—it must be resolved. The option "Advance additional funds without review" is incorrect; advancing more funds without resolving the existing lien would increase risk and violate prudent lending and the loan agreement. Exam tip: All contractual conversion conditions are conjunctive ('and'); failure of any one prevents conversion.

Was this explanation helpful?

More Origination Questions

Before the team acts on a servicing handoff check, a closing coordinator must address Asset Verification and Reserves. Which response is most defensible?

An MLO is reviewing procedures for a case where a cost changes after the Closing Disclosure has already been provided. What is the proper handling?

During a post-application update, a quality-control reviewer encounters a Credit Analysis and Evaluation issue. Which response should avoid a shortcut that would misapply the rule?

A construction-to-permanent loan will disburse in 5 draws over 11 months before the permanent phase begins. Which Regulation Z appendix provides a disclosure method for multiple-advance construction transactions?

Before closing, the team discovers that a borrower asks which upfront charge can be collected before intent to proceed. What is the safest compliant answer?

A construction loan agreement allows advances only after documented completion of specified work. A builder requests the next draw, but no completion evidence has been provided. What should occur?

Before releasing the final construction draw, which combination most directly supports project completion and clear collateral?

A construction-to-permanent loan will convert to a substantially higher fully amortizing payment. Which payment is especially important when assessing the borrower's long-term repayment capacity?

A branch manager asks about a loan file because a processor wants to omit known monthly obligations from underwriting. What should happen?

Before closing, the team discovers that a processor wants to omit known monthly obligations from underwriting. What is the safest compliant answer?

People Also Study

Related Study Resources

Practice More MLO Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your SAFE MLO exam.

Start Practicing