Mortgage exam diagrams · Chapter 7 of 15
Fee tolerances
Compare the total of a tolerance group with its permitted increase.
Inspect the file


Borrower file
Assume two charges qualify for the 10% cumulative tolerance group. Valid baseline estimates are $600 and $400. Final charges are $750 and $370. There is no valid revised baseline.
Illustrative photographs and simulated fileTest the diagram
Move the group’s final total above and below its ceiling. Observe when the excess first appears.
Work through the file
The group starts at $1,000 and can reach $1,100. Actual charges add to $1,120. The excess in this file is $20.
Check the exam trap
Checking each individual line against 110% can produce a different answer. The comparison for this group uses the aggregate.
- Cumulative group: cure $20
Compare a second file
Compare the same $100 increase in three different classifications. Assume no valid revised estimate. Select each group to read the effect.
- Zero tolerance: cure $100
- 10% aggregate: cure $0
- No numeric cap: cure $0
Classify before comparing amounts
- Provider selection
- Whether shopping was allowed and whether the borrower chose a provider on the written list can affect which rule applies.
- Baseline revision
- Before accepting a higher baseline, document the qualifying reason and timing for a permitted revision. A later invoice alone does not automatically reset the estimate.
Audit the group before calculating a cure
Two charges belong in the same 10% cumulative group. Their valid estimates are $600 and $400. Final charges are $750 and $330. Assume no permitted baseline revision.

Which invoices belong in the same test?
Read the evidence
Match provider selection and service classification before adding the final charges. Compare the combined group with its valid baseline and keep zero-tolerance charges outside it.
- Keep the group intact
The baseline is $1,000 and its ceiling is $1,100. Applying a separate 10% ceiling to each line would change the test.
- Reconcile both invoices
One line rises $150 and the other falls $70. The final combined $1,080 is within the ceiling.
- Isolate other categories
A separate charge subject to zero tolerance must be tested against its own baseline. Unused room in this group cannot offset its increase.
Make the decision
Change the facts
Practice by exam topic
Open a file, trace the decision rule and test it against the facts.
TRID changed circumstances
- File evidence
- An appraisal reveals a property condition the creditor did not reasonably know, increasing a covered service cost.
- Decision rule
- Check for a permitted revision, its causal connection to the affected charge and the timing of redisclosure. An unrelated cost increase keeps its applicable baseline.
Disclosure terms: servicing transfers, lender credits
- File evidence
- A borrower receives a lender credit at closing and a servicing-transfer notice months later.
- Decision rule
- A lender credit can offset closing costs and may reflect pricing. Historical yield spread premium described rate-linked broker compensation; modern compensation rules govern current transactions. A servicing transfer changes who handles payments and can occur without a change in ownership.
Tolerances and cures
- File evidence
- A required service uses an unaffiliated provider selected from the creditor’s written list after shopping was allowed.
- Decision rule
- Classify each charge before testing the group. Creditor or affiliate charges and required services with no shopping generally receive zero tolerance. Certain listed-provider charges and recording fees share a 10% aggregate limit. Check valid revisions and cure requirements.

What needs to match across the two versions?
Read the evidence
Use the same service and provider classification and verify the permitted estimate baseline before testing the final amount.
For the post-consummation good-faith cure, refund the excess and deliver or place the corrected disclosure in the mail no later than 60 calendar days after consummation. A cure is different from a valid pre-closing baseline revision.
12 CFR § 1026.19 ↗Loan Estimate timing and revisions
- File evidence
- A borrower waits beyond the LE period for indicating intent to proceed. The creditor offered no longer period.
- Decision rule
- Charges generally expire if intent is not indicated within ten business days after the LE is provided. Track permissible revision events and delivery deadlines, the CD cutoff and any necessary tolerance correction.
When a permissible event justifies revision, the creditor generally sends the revised estimate within three business days of sufficient information. The consumer must receive it at least four business days before consummation, and it cannot be issued on or after provision of the CD. Apply the corrected-CD and refund rules where a tolerance violation remains.
12 CFR § 1026.19 ↗Fees, compensation, fee splitting
- File evidence
- Two settlement providers split a charge. One performed no service for its share.
- Decision rule
- Trace the charge, the work performed and how payment was allocated. Evaluate unearned fee splitting, referral arrangements and any required revised disclosures as separate issues.