EstatePass

An inspector is reviewing the plumbing system of a commercial building. Which of the following is a requirement for the installation of water supply and drainage piping?

ICC B2 exam practice question · General Administration

An inspector is reviewing the plumbing system of a commercial building. Which of the following is a requirement for the installation of water supply and drainage piping?

  • APiping must be installed in a straight line
  • Piping must be installed with a minimum slope of 1/4 inch per foot
  • CPiping must be installed with a maximum slope of 1/4 inch per foot
  • DPiping must be installed with a minimum slope of 1/8 inch per foot

Exam tip

Understanding the required slopes for plumbing piping is crucial for proper installation and function.

Why B is correct

The IBC requires that water supply and drainage piping be installed with a minimum slope of 1/4 inch per foot to ensure proper drainage and prevent backups.

Practice 10 more General Administration questions

Timed mock exams, a wrong book and flashcards — one subscription covers every contractor exam line.

Start studying free