An approved agency prepares a special-inspection report under 2021 IBC 1704.2.4. What must the report indicate about the work inspected or tested?
- AWhether the contractor met the project profit target
- BWhether the project will finish on the original schedule
- Whether the work conforms to the approved construction documents
- DWhether the agency has taken over the contractor's construction supervision
Where to look it up
https://core-docs.s3.amazonaws.com/documents/asset/uploaded_file/3836/Lennox/3042180/2021_International_Building_Code.pdf
Why C is correct
The report addresses conformity of the inspected or tested work to the approved construction documents. The reporting requirement does not transfer scheduling, business management or construction supervision to the inspection agency. Source: 2021 IBC 1704.2.4; https://core-docs.s3.amazonaws.com/documents/asset/uploaded_file/3836/Lennox/3042180/2021_International_Building_Code.pdf