A commercial building is being constructed with a steel frame. During the framing inspection, the inspector notices that the steel beams are not labeled with their size and grade. Which of the following actions should the inspector take?

ICC B2 exam practice question · General Administration

A commercial building is being constructed with a steel frame. During the framing inspection, the inspector notices that the steel beams are not labeled with their size and grade. Which of the following actions should the inspector take?

  • Order the contractor to label the beams immediately.
  • BIssue a notice of deficiency and allow the contractor to correct the issue within a week.
  • CAccept the beams as is and move on to the next phase of the inspection.
  • DRequest a meeting with the project engineer to discuss the labeling requirements.

Exam tip

Always ensure that materials meet the labeling requirements as specified in the IBC.

Why A is correct

According to Section 1003.2.2 of the 2021 International Building Code, steel beams must be labeled with their size and grade. The inspector should order the contractor to label the beams immediately to ensure compliance with the code.