EstatePass
All Parts60 Questions

Project Management

Construction methods, materials, safety, and blueprint reading for Florida contractors.

500 questions available4.5 hours70% to pass
Difficulty Breakdown
Easy168 (34%)
Medium251 (50%)
Hard81 (16%)

Practice Questions

E

Construction Methods, Materials, Tools & Equipment

201Q

What is the minimum R-value required for wall insulation in Florida Climate Zone 2?

easy

What is the maximum recommended spacing between drywall screws when attaching to wood studs?

easy

In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?

medium

What is the minimum concrete cover required for rebar in a concrete footing that will be in direct contact with soil?

medium

What is the standard minimum concrete cover required for #4 rebar in a residential foundation wall according to Florida Building Code?

medium

A concrete slab measures 40 feet by 60 feet and is 6 inches thick. How many cubic yards of concrete are needed?

easy

During welding inspection, what indicates a proper penetration weld?

medium

When setting batter boards for a building foundation, what is their primary purpose?

easy

What is the standard on-center spacing for wood studs in residential construction?

easy

For a residential floor system with 16" joist spacing, what is the maximum allowable span for 2x10 Southern Pine joists (Grade #2) supporting a live load of 40 psf?

hard

A project requires 150 cubic yards of fill material with 95% compaction. The soil has a shrinkage factor of 15%. How many cubic yards of loose material must be ordered?

hard

During window installation, you discover the rough opening is 1/4 inch too small on one side. What is the best corrective action?

medium

What type of mortar is typically specified for below-grade masonry construction in contact with soil?

medium

During a concrete pour, the ready-mix truck is delayed and concrete begins to set before placement is complete. What is the most appropriate action?

medium

What is the designation for a #5 rebar in terms of diameter?

easy

What is the minimum R-value for ceiling insulation required by the Florida Building Code in Climate Zone 2?

medium

When installing concrete masonry units (CMU), what is the standard height of each course including the mortar joint?

easy

A contractor discovers that the soil bearing capacity at a job site is 2,000 psf, but the foundation design requires 3,000 psf. What is the most appropriate solution?

medium

A 2×10 Douglas Fir joist with a span of 16 feet is loaded beyond its capacity according to span tables. What is the best solution?

medium

What is the minimum curing time for concrete before forms can be stripped from vertical surfaces?

medium

What welding process is most commonly used for structural steel connections in building construction?

medium

When installing CMU blocks, which mortar type provides the highest compressive strength?

medium

What is the minimum curing time before concrete forms can typically be stripped from vertical surfaces?

easy

In Florida's climate, what is the recommended minimum R-value for ceiling insulation in residential construction?

medium

What is the primary advantage of Structural Insulated Panels (SIPs) over conventional stick framing?

medium

A flat roof system in Florida requires a slope for drainage. What is the minimum slope recommended?

easy

What is the minimum concrete cover required for #5 rebar in a concrete footing exposed to earth and weather according to ACI 318?

medium

You're installing a built-up roof system on a commercial building in Miami. The roof deck is slightly damp from morning dew. What should you do?

medium

When installing a vapor barrier in Florida construction, where should it typically be placed?

hard

What is the proper procedure when a concrete cylinder test fails to meet the specified compressive strength?

hard

+ 171 more questions

F

Safety

186Q

A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?

easy

A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?

medium

Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?

medium

A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?

easy

Your electrician needs to perform maintenance on a 480V panel. According to OSHA lockout/tagout procedures, what is the maximum voltage that can be worked on without de-energizing the circuit?

hard

Which OSHA standard specifically addresses construction industry safety and health regulations?

easy

A fire extinguisher rated as Class K is most appropriate for use on which type of fire?

easy

A mobile crane with a 150-foot boom is being used to lift materials. What is the minimum distance this crane must maintain from overhead power lines carrying 50 kV?

medium

Workers are installing roofing materials on a building with a 4:12 pitch roof. At what height above the lower level must fall protection be implemented?

medium

A worker must enter a confined space to perform maintenance. The space has been tested and found to have 19% oxygen content. What action should be taken?

medium

A mobile crane with a 150-foot boom is operating near power lines. What is the minimum safe distance that must be maintained from energized power lines rated at 50kV?

medium

A job site has a 40-foot high building under construction. What is the required guardrail height for roof edge protection?

easy

Scaffold planks must be able to support how many times their maximum intended load without failure?

medium

What is the minimum number of points of contact required when climbing a ladder?

easy

A trench is 12 feet deep in Type C soil (least stable). If sloping is used instead of shoring, what is the minimum slope ratio required?

hard

During a confined space rescue, what is the maximum time an entrant should remain in the space before rotation or removal?

hard

An electrical panel is being serviced using lockout/tagout procedures. Who is authorized to remove the lockout device?

easy

How often must scaffolds be inspected according to OSHA standards?

medium

Hard hats must be replaced when they show signs of damage or after what maximum time period?

easy

A construction site fire extinguisher system requires extinguishers to be placed so that travel distance does not exceed what maximum distance?

medium

During a roofing project, a worker notices that the guardrail system appears damaged. What is the minimum top rail height requirement for guardrail systems according to OSHA standards?

easy

A contractor receives a Safety Data Sheet that shows a chemical has a flash point of 85°F. How should this material be classified and stored?

medium

An electrical panel needs maintenance work. The lockout/tagout procedure requires that the energy source be:

medium

When disturbing painted surfaces in a building built in 1968, what is the minimum area of paint disturbance that triggers EPA RRP (Renovation, Repair, Painting) Rule requirements?

medium

A construction site has multiple buildings under construction. What is the maximum distance between fire extinguishers for Class A (ordinary combustibles) fires?

easy

A crane operator is lifting a 15,000-pound load with a crane rated at 25,000 pounds capacity. The load chart shows the crane's capacity at the current boom length and angle is 18,000 pounds. What is the safety factor for this lift?

hard

A trench excavation is 15 feet deep and 4 feet wide. The estimated cost of sloping versus shoring is: sloping requires 200 cubic yards of additional excavation at $12/cubic yard, while shoring costs $2,800. What is the cost difference?

medium

During a confined space rescue, what is the maximum time allowed for initial response before emergency services must be contacted?

hard

A crane is lifting a 8,000-pound load with a 4-part line (4:1 mechanical advantage). If the crane's load block weighs 500 pounds, what is the total load on the crane's hoist line?

hard

Under the Globally Harmonized System (GHS), what information must be included on a Safety Data Sheet (SDS)?

hard

+ 156 more questions

G

Reading Plans and Specifications

113Q

A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?

medium

According to the Florida Building Code, what is the minimum clear width required for an accessible doorway?

medium

Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?

hard

The Florida Building Code requires that construction documents be prepared by whom for commercial buildings over what square footage?

hard

A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?

medium

An accessible parking space detail shows dimensions of 8 feet wide with a 5-foot access aisle. A van-accessible space is also required. What should be the width of the van-accessible space?

hard

What is the minimum clear width required for an accessible door opening under ADA guidelines?

medium

On a plumbing plan, what does the symbol 'WC' typically indicate?

easy

A detail drawing shows a wall section at a scale of 1/2" = 1'-0". If a dimension measures 3 inches on the drawing, what is the actual dimension?

medium

In CSI MasterFormat, which division covers concrete work?

easy

A site plan shows a building setback dimension of 25'-0" from the property line, but the building footprint appears to be only 20'-0" from the property line when scaled. As the general contractor, what is your primary concern?

hard

On plumbing drawings, what does the abbreviation 'DHW' typically represent?

easy

A plumbing plan shows a circle with an 'X' inside it. What does this symbol represent?

easy

A site plan shows a building setback of 25 feet from the front property line. If the lot depth is 150 feet and the building depth is 80 feet, what is the maximum rear setback that can be achieved?

medium

On electrical plans, a square with an 'X' inside connected to a line typically represents what type of electrical component?

easy

A detail drawing shows a scale of 1/2" = 1'-0". If a dimension measures 3 inches on the drawing, what is the actual dimension?

medium

According to the Florida Building Code, what is the maximum allowable slope for an accessible ramp?

easy

CSI MasterFormat Division 26 specifications would typically include which building systems?

medium

On plumbing drawings, what does the symbol 'FD' typically indicate?

easy

In the CSI MasterFormat system, which division covers thermal and moisture protection?

medium

On an electrical plan, what does a circle with the letters 'GFCI' indicate?

easy

You notice a discrepancy between the architectural drawings and structural drawings regarding beam locations. What is the best course of action?

medium

According to the plumbing symbols on a set of plans, what does 'CW' typically indicate?

easy

A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?

medium

During construction, a contractor discovers that the shop drawings for structural steel conflict with the architectural drawings. What should be the contractor's first course of action?

medium

According to the Florida Building Code, what is the maximum slope allowed for an accessible ramp?

easy

On a structural plan, you see the notation '#4 @ 12" O.C.' What does this specify?

easy

On a detail drawing, what does a thick solid line typically represent?

easy

A site plan shows an existing grade of 102.5' and a proposed grade of 104.0' at a specific location. How much fill is required at this point?

easy

A grading plan shows contour lines with 2-foot intervals. If you count 5 contour lines between two points, what is the elevation difference?

easy

+ 83 more questions

About Project Management

60

Scored Questions

4.5h

Time Limit

4.5m

Per Question

The Project Management section is one of three independently scored parts on the Florida General Contractor licensing exam administered by PSI. You must score at least 70% to pass this part. The exam is open book — you may bring up to 15 approved reference materials into the testing center, but with only 4.5 minutes per question, efficient tab-marking and familiarity with your references are essential.

Construction methods, materials, safety, and blueprint reading for Florida contractors.

What's Tested: 3 Content Areas

E

63%

Construction Methods, Materials, Tools & Equipment

Site work, earthwork, concrete, masonry, wood framing, steel, innovative techniques (tilt-up/SIP/ICF), energy-efficient construction.

~38 questions on the exam

F

20%

Safety

OSHA standards (scaffolding/trenching/fall protection), asbestos/lead paint/hazardous waste.

~12 questions on the exam

G

17%

Reading Plans and Specifications

Construction drawings, architectural/engineering symbols, shop drawings, specifications, ADA requirements.

~10 questions on the exam

Study Strategy for Project Mgmt

Prioritize by Weight

Focus on Construction (63%) and Safety (20%) first — they cover the most questions.

Tab Your References

With only 4.5 min/question, you need to find answers fast. Color-code tabs by content area.

Master the Math

Calculation questions (payroll, overhead, bidding) are common. Practice with our math calculator until the formulas are second nature.

Know FL Statutes

Florida-specific rules (Ch. 489 F.S., FAC 61G4) are heavily tested. Bookmark these sections in your reference books.

Simulate Exam Conditions

Take timed 60-question practice sessions to build stamina for the 4.5-hour exam.

Review Wrong Answers

Use the wrong book feature to revisit missed questions. Understanding why an answer is wrong is as important as knowing the right answer.

Frequently Asked Questions

How many questions are on the Project Management section of the FL contractor exam?

The Project Management section contains 60 scored questions. You must answer them within 4.5 hours. The exam is administered by PSI and is open book — you may bring approved reference materials.

What is the passing score for Project Mgmt?

You need a score of 70% or higher to pass the Project Management section. That means you must answer at least 42 out of 60 questions correctly.

Is the Project Mgmt exam open book?

Yes. The Florida General Contractor exam is open book for all three parts, including Project Mgmt. You are allowed to bring approved reference books into the testing center. However, time management is critical — you cannot look up every answer.

How long do I have to complete the Project Mgmt section?

You have 4.5 hours (270 minutes) to complete all 60 questions in the Project Management section. That averages to about 4.5 minutes per question.

Master Project Mgmt

Practice all 500 questions interactively with progress tracking and adaptive difficulty.

Start Free Practice