A contractor discovers that the soil bearing capacity at a job site is 2,000 psf, but the foundation design requires 3,000 psf. What is the most appropriate solution?
Correct Answer
A) Use a deeper foundation or soil improvement methods
When soil bearing capacity is insufficient, the foundation must be redesigned to reach more competent soil at greater depth or soil improvement methods must be used. Simply increasing width may not be sufficient for such a significant capacity difference.
Why This Is the Correct Answer
CORRECT_ANSWER - When soil bearing capacity is significantly insufficient (2,000 psf vs required 3,000 psf), the foundation system must be fundamentally redesigned. Deep foundations like piles or caissons can transfer loads to more competent soil layers below, or soil improvement methods like compaction grouting can increase the bearing capacity. This addresses the root problem rather than attempting inadequate workarounds that could lead to structural failure.
Why the Other Options Are Wrong
Option B: Increase the foundation width to reduce bearing pressure
Reducing building loads by changing materials addresses the symptom but not the fundamental soil capacity issue. The load reduction required would likely compromise the building's intended use and may still not be sufficient to bridge the 1,000 psf capacity gap safely.
Option C: Reduce the building load by changing materials
While increasing foundation width reduces bearing pressure, the capacity deficit is too large (50% increase needed). The required width increase would be impractical and may not fit within property boundaries or building constraints. This approach also doesn't account for potential settlement issues.
Memory Technique
Think 'DIG DEEP' - when soil capacity is Deficient, you must go deeper with piles/caissons or Improve the Ground through soil modification rather than surface band-aids.
Reference Hint
Florida Building Code, Chapter 18 (Soils and Foundations) and IBC Chapter 18 for soil bearing capacity requirements and foundation design criteria
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A site plan shows existing grade at elevation 102.5' and proposed grade at elevation 105.0' at a specific point. How much fill is required at this location?
Next Question
You discover a discrepancy between the architectural drawings and structural drawings regarding beam locations. The project specifications state that structural drawings take precedence. However, following the structural drawings would create ADA compliance issues. What should you do?
