When setting batter boards for a building foundation, what is their primary purpose?
Correct Answer
B) To establish and maintain building lines and elevations during excavation
Batter boards are temporary wooden frames set up at the corners of a building site to establish and maintain the exact building lines and elevations. They allow string lines to be stretched between them to guide excavation and foundation work while remaining undisturbed by construction activities.
Why This Is the Correct Answer
Batter boards are specifically designed to establish and maintain precise building lines and elevations during the construction process. They are positioned outside the excavation area so they won't be disturbed during digging and foundation work. String lines stretched between batter boards create reference points that guide excavation depth, foundation placement, and ensure the building is constructed in the exact location and orientation specified in the plans. This system allows contractors to maintain accuracy throughout the foundation phase even as heavy equipment operates in the work area.
Why the Other Options Are Wrong
Option C: To provide temporary storage for construction materials
Property boundary lines are established by licensed surveyors using permanent markers and monuments. Batter boards are temporary construction layout tools used specifically for individual building placement, not property line demarcation.
Option D: To support concrete forms during pouring
Batter boards are not designed or intended for material storage. They are lightweight wooden frames positioned specifically for surveying and layout purposes, not for bearing the weight of construction materials.
Memory Technique
Think 'BATTER = BETTER reference' - batter boards provide better, undisturbed reference points for building lines and elevations throughout the foundation process.
Reference Hint
Look up 'Site Layout and Excavation' or 'Foundation Layout' chapters in construction reference materials, specifically sections on surveying and building layout procedures.
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass