Scaffold planks must be able to support how many times their maximum intended load without failure?
Correct Answer
C) 4 times the maximum load
OSHA requires scaffold planks to support at least 4 times the maximum intended load as the safety factor. This provides adequate margin for dynamic loading and material variations.
Why This Is the Correct Answer
OSHA 29 CFR 1926.451(a)(1) specifically requires that scaffold planks must be capable of supporting at least 4 times the maximum intended load without failure. This 4:1 safety factor accounts for dynamic loading conditions, material degradation over time, and variations in material strength. The safety factor ensures that even under unexpected stress conditions or when materials don't meet exact specifications, the scaffold will remain safe for workers.
Why the Other Options Are Wrong
Option A: 3 times the maximum load
A 5:1 safety factor exceeds OSHA requirements and would be unnecessarily conservative, potentially leading to overengineered and more expensive scaffold systems.
Option B: 5 times the maximum load
A 2:1 safety factor is insufficient for scaffold planks as it doesn't provide adequate margin for the dynamic loading and impact forces that scaffolds experience during construction work.
Memory Technique
Use the mnemonic 'FOUR FLOORS' - scaffold planks (the floors workers stand on) must support FOUR times their intended load
Reference Hint
OSHA 29 CFR 1926.451 - Scaffolds General Requirements, specifically subsection (a)(1) covering structural integrity requirements
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A commercial project requires 3,200 square feet of VCT flooring. Including waste factor, how many cartons should be ordered if each carton covers 45 square feet?
Next Question
A contractor is reviewing a plumbing plan that shows a 4-inch sanitary sewer line running 150 feet with a minimum slope of 1%. What is the total vertical drop of this pipe?