EstatePass
NASCLAProject Mgmthard22% of exam part

Your project requires coordination between structural steel erection and concrete placement. The steel subcontractor can erect 50 tons per day, and you have 800 tons total. Concrete can be placed 2 days after steel erection begins in each area. If concrete crews need 12 days total, when should concrete operations start to finish simultaneously with steel?

Correct Answer

B) Day 6

Steel duration: 800 ÷ 50 = 16 days. Steel finishes day 16. Concrete needs 12 days and must finish day 16, so concrete starts day 5. With 2-day lag after steel start, concrete can begin day 3, but to finish simultaneously: 16 - 12 + 2 = day 6.

Answer Options
A
Day 4
B
Day 6
C
Day 5
D
Day 7

Why This Is the Correct Answer

Steel duration: 800 ÷ 50 = 16 days. Steel finishes day 16. Concrete needs 12 days and must finish day 16, so concrete starts day 5. With 2-day lag after steel start, concrete can begin day 3, but to finish simultaneously: 16 - 12 + 2 = day 6.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.