A site requires 2,400 cubic yards of fill material. The borrow pit material has a swell factor of 25%. How many cubic yards must be excavated from the borrow pit?

Correct Answer

D) 1,920 cubic yards

Bank measure = Loose measure ÷ (1 + swell factor). 2,400 ÷ 1.25 = 1,920 cubic yards

Answer Options
A
2,400 cubic yards
B
3,000 cubic yards
C
2,000 cubic yards
D
1,920 cubic yards

Why This Is the Correct Answer

Bank measure = Loose measure ÷ (1 + swell factor). 2,400 ÷ 1.25 = 1,920 cubic yards

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.