You discover that a subcontractor has left the site without completing punch list items worth $3,200. The subcontractor's contract has a 10% retention held. The total subcontract value was $45,000. What options do you have?

Correct Answer

D) Can use retention funds to complete the work

Retention funds ($4,500) can be used to complete punch list items ($3,200) when a subcontractor fails to complete their obligations.

Answer Options
A
Must pursue legal action for the $3,200
B
No recourse since retention ($4,500) exceeds punch list cost
C
Must complete the work at your own expense
D
Can use retention funds to complete the work

Why This Is the Correct Answer

Retention funds ($4,500) can be used to complete punch list items ($3,200) when a subcontractor fails to complete their obligations.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.