EstatePass
NASCLAProject Mgmtmedium22% of exam part

A concrete crew can place 150 cubic yards per day. A project requires 2,250 cubic yards of concrete to be placed over 12 working days. How many crews are needed?

Correct Answer

D) 1.25 crews

Total concrete needed: 2,250 cy. Available crew-days: 12 days. Concrete per crew-day: 150 cy. Required crews: 2,250 ÷ (12 × 150) = 1.25 crews.

Answer Options
A
3 crews
B
2 crews
C
1 crew
D
1.25 crews

Why This Is the Correct Answer

Total concrete needed: 2,250 cy. Available crew-days: 12 days. Concrete per crew-day: 150 cy. Required crews: 2,250 ÷ (12 × 150) = 1.25 crews.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.